Takt and cycle time comparison
Compare takt with cycle time. Calculate parallel stations using complete units within the available time and identify infeasible cycles.
The example value has been entered. Check it immediately or change the value.
Input is processed in the browser. Refreshing returns a sample value.
Instructions and example
Takt=available minutes/demand. Whole units per station=floor(available minutes/cycle minutes); stations=ceil(demand/whole units per station).
Takt is 1.5 minutes, required load is 120%, and parallel stations total 2.
Identical stations start together and each completes whole units sequentially; work cannot be split. A cycle longer than available time is infeasible. This is not staffing advice. Decimal inputs use exact fractions up to 30 significant digits, 30 decimal places and exponent magnitude 30. Displayed fractional results round to 12 significant digits; integer counts use exact decisions.
Frequently asked questions
What happens when cycle time exceeds takt?
Takt=available minutes/demand. Whole units per station=floor(available minutes/cycle minutes); stations=ceil(demand/whole units per station).
How many parallel stations does the public cycle require?
Takt is 1.5 minutes, required load is 120%, and parallel stations total 2.
Calculation criteria and reference materials
- Lean Enterprise Institute — Takt Time
Defines takt as available production time divided by demand.
Verification of calculation criteria: · Calculation·verification principles · Report errors