PERT duration estimate
Expected duration=(optimistic+4×likely+pessimistic)/6; variance=((pessimistic−optimistic)/6)². Review your assumptions.
The example value has been entered. Check it immediately or change the value.
Input is processed in the browser. Refreshing returns a sample value.
Instructions and example
Expected duration=(optimistic+4×likely+pessimistic)/6; variance=((pessimistic−optimistic)/6)².
Design has expected duration 3.66666666667; the total is 10.
Rows are name,optimistic,likely,pessimistic with optimistic≤likely≤pessimistic. Totals assume sequential tasks and independent variances. Each list supports 100 rows and 20000 characters per input; names containing commas are unsupported.
Frequently asked questions
How is the likely duration weighted in PERT?
Expected duration=(optimistic+4×likely+pessimistic)/6; variance=((pessimistic−optimistic)/6)².
What is the expected duration of Design followed by Build?
Design has expected duration 3.66666666667; the total is 10.
Calculation criteria and reference materials
- PMI — Three-point estimating
Reference for the model and assumptions, not a guarantee of results.
Verification of calculation criteria: · Calculation·verification principles · Report errors